Summary of partial demo in a warehouse located in Minnetonka, requiring estimate for labor, materials, lift, and permitting costs. They want some of their walls eliminated in order to reduce obstacles on the work floor. Intech would just be facilitating the electrical portions. Relevant video of each space and required SOW is attached below.
Office Area
Video 0061: (1) Switch relocation (recessed)
Video 0062: (2) Switch Relocations (recessed), (2) Outlet Eliminations (recessed)
I said there was only one outlet in this video, but there are two in that wall. You can see the other one underneath the desk with a wire plugged into it at the 0:05 in the video. Both outlets will need to be eliminated. Also toward the end of the video, I referred to the switch on the wall as an outlet at 0:21, but meant to say switch, to clarify.
Video 0063: (2) Switch Relocations (recessed), (1) Outlet Elimination (recessed)
Video 0092: (1) Thermostat relocation (surface mounted), (1) Outlet Elimination (recessed)
Warehouse
Video 0064: Warehouse Overview
Video 0080: Demo wall #1 – (1) outlet relocated to shared bathroom wall (recessed), (1) jbox relocation (surface mounted), and (1) conduit relocation (surface mounted), (1) BX run relocation (surface mounted), (1) outlet+switch elimination for garbage disposal(I think?) (recessed).
Video 0080.2: Demo wall #1 – (3) relocations of low voltage cables (or elimination if not being used), (1) fire system jbox and equipment relocation (surface mounted)
Video 0081: Demo wall #1 – (1) Low volt key scanner elimination
Video 0082: Demo wall #1 – (1) light switch relocation with associated junction box and conduit (surface mounted), (1) thermostat relocation (or elimination if not used),
Video 0083 – Demo wall #1 – (1) triple switch relocation (recessed)
Video 0085: Demo wall #1 (upper level) – (1) Contactor(?) relocation, (1) fire system jbox and equipment relocation (surface mounted), (~2) low voltage wire relocations
Video 0086: Demo wall #1 (upper level) – (1) conduit run relocation
Video 0087: Demo wall #1 (upper level)
Video 0066: Warehouse Office Overview
Video 0074: Wall #3 (Warehouse Office Wall) – (1) double switch relocation
Video 0073: Warehouse Office – (1) light switch elimination (recessed), (2) light eliminations (recessed),(2) ceiling jbox eliminations (recessed), (2) outlet eliminations (recessed)
Video 0075: Behind/Back of Warhouse Office (Overview)
Video 0068: N/A (Warehouse Storage Room #1 Overview)
Video 0076: Warehouse Storage Room #1: (1) elimination of button switch (surface mounted), (2) elimination of thermostats (surface mounted), (1) elimination of misc./broken low voltage device (surface mounted), (1) double gang/double switch relocation for ceiling lights (recessed)
Video 0077: N/A (additional info for Warehouse Storage Room #1)
Video 0078: Transitions to Warehouse Storage Room #2 – (2) conduit relocations (surface mounted)
Video 0069: Warehouse Storage Room #2 – (1) conduit run with (2) associated outlet boxes and (1) associated jbox (surface mounted); (1) conduit run with (1) associated jbox (surface mounted)
Image 0070: Warehouse Storage Room #2 – 2nd listed conduit run associated jbox
Video 0071: Warehouse Storage Room #3 – Opposite side of the wall of the above “Warehouse Storage Room #2 2nd listed conduit run associated jbox” (part 1)
Video 0072: Warehouse Storage Room #3 – Opposite side of the wall of the above “Warehouse Storage Room #2 2nd listed conduit run associated jbox” (part 2) – (1) conduit run with (1) associated outlet boxes and (1) associated jbox (surface mounted)
Video 0079: Specification of what is *not* required in Warehouse Storage Room #3
Video 0088: Demo Wall #2: Specification of what is *not* required regarding large retired raceway
Video 0089: Demo Wall #2: (1) Emergency light relocation
Video 0091: Demo Wall #2: (1) specification of what is *not* required, (2) low voltage wire relocations, (1) jbox with associated flex relocation, (1) low voltage jbox with associated conduit/wire
SUMMARY:
~50–55 total scoped electrical actions. Heavy on relocations (dominant), then eliminations, then low voltage + conduit work. This is a mid-complexity demo-prep job, not light.
CLEAN SOW SUMMARY (WITH TOTAL COUNTS)
OFFICE AREA
Switches
- Relocations: 5
- (all recessed)
Outlets
- Eliminations: 4
Thermostats
- Relocations: 1 (surface)
WAREHOUSE – DEMO WALL #1
Power / Devices
- Outlet relocations: 1
- Outlet eliminations (incl. disposal): 1
- Switch relocations: 2
- Triple switch relocations: 1
Junction Boxes / Conduit / BX
- J-box relocations: 2
- Conduit relocations: 2
- BX run relocations: 1
Thermostats
- Relocations or eliminations: 1
Low Voltage
- Cable relocations/eliminations: ~5
- Key scanner eliminations: 1
Fire System
- J-box + equipment relocations: 2
Misc Equipment
- Contactor relocation: 1
WAREHOUSE OFFICE (SEPARATE AREA)
Switches
- Relocations: 1
- Eliminations: 1
Lighting
- Light eliminations: 2
Junction Boxes
- Ceiling j-box eliminations: 2
Outlets
- Eliminations: 2
STORAGE ROOM #1
Switches / Controls
- Button switch elimination: 1
- Double switch relocation: 1
Thermostats
- Eliminations: 2
Low Voltage
- Device elimination: 1
STORAGE ROOM #2
Conduit Runs
- New/relocated conduit runs: 2
Boxes tied to conduit
- Outlet boxes: 2
- J-boxes: 2
STORAGE ROOM #3
Conduit
- Conduit runs: 1
Boxes
- Outlet boxes: 1
- J-boxes: 1
DEMO WALL #2
Lighting
- Emergency light relocation: 1
Low Voltage
- Wire relocations: 2
- Low voltage j-box relocation: 1
Power / Boxes
- J-box + flex relocation: 1
GRAND TOTALS (AGGREGATED)
SWITCHES
- Relocations: ~10
- Eliminations: ~2
OUTLETS
- Relocations: 1
- Eliminations: ~7
LIGHTING
- Light eliminations: 2
- Emergency light relocations: 1
THERMOSTATS
- Relocations: 2
- Eliminations: 2
JUNCTION BOXES
- Relocations: ~6
- Eliminations: 2
CONDUIT / BX
- Conduit relocations/runs: ~6
- BX relocations: 1
LOW VOLTAGE
- Wire relocations/eliminations: ~8–10
- Device eliminations: 2
FIRE SYSTEM
- Equipment relocations: 2
SPECIALTY
- Contactor relocations: 1